Project Management Weekly Challenge 7_Updating

 

Project Initiation: Starting a Successful Project (W3)


1. Which of the following responsibilities does project management include?

A: Oversee the scope, schedule, budget, and quality of a project

2. Does the project sponsor fund the project?

A: Sometimes. The project sponsor plays a vital leadership role, which sometimes includes funding the project.

3. Which stakeholders benefit directly (not indirectly) from a project’s success? Select all that apply.

A.
- Primary stakeholders

(Which stakeholders are indirectly impacted by a project's success? - Secondary stakeholders)

4. Which responsibilities belong to project team members?

A: Use technical expertise and interpersonal skills to complete day-to-day tasks

5. What is the purpose of a stakeholder analysis?

A: Identify stakeholders and determine their involvement in a project

6. Which of the following activities are steps in a stakeholder analysis? Select all that apply.

A:
- Assess each stakeholder’s level of interest and influence
- ist the stakeholders impacted by the project

7. What does the acronym RACI stand for?

A: Responsible, Accountable, Consulted, Informed

8. Which of the following is true of someone who is accountable in a RACI chart?

A: Ensures the work gets completed

9. As a project manager, you make considerations when building a team. You decide how many people should be on the team, if they have the time to work on the project, and what expertise each team member needs for their tasks. What else should you consider when building a team?

A:
-Team member motivation
-Necessary skills for the project

10. As a project manager, you’re prioritizing stakeholders with a power grid. One stakeholder has low power and high interest. What level of engagement should the team have with the stakeholder?

A: Show consideration

11. Which of the following responsibilities typically belong to the project manager? Select all that apply.

A:
- Develop the project management plan
- Direct project work and report on progress to stakeholders
- Control change and monitor project quality

12. Which three of the following responsibilities can belong to the project sponsor?

A:
- Fund the project.
- Ensure that the project delivers the agreed-upon value to the business.
- Play a key leadership role throughout the project.

13. Who uses technical and interpersonal skills to carry out day-to-day project tasks?

A: Project team members

14. Which of the following statements are true of RACI charts? Select all that apply.

A:
- Define project roles and responsibilities to ensure efficiency
- Determent which stakeholders are responsible for which tasks

15. Who is responsible for overseeing the scope, schedule, budget, and quality of a project?

A: Project manager

16. Which of the following people are likely to be primary stakeholders in a project? Select all that apply/

A:
- The project sponsor
- The project team
- The project client.

17. Fill in the blank: Stakeholder analysis is the process of identifying stakeholders and grouping them by______.

A: Interest and influence.

18. What is the first step in a stakeholder analysis?

A: List the stakeholders impacted by the project

19. What is the main benefit of making a RACI chart?

A: Determines which stakeholders should fill which roles during a project

20. In what two ways do RACI charts help project managers communicate effectively with stakeholders?

A:
- Map out each person's roles and responsibilities
- Eliminate confusion and overlapping work at the task level

Comments

Popular posts from this blog

Project Management Weekly Challenge 2_Updating

  Foundations of Project Management (W2) 1. Suppose that as a project manager, you speak with stakeholders to determine which tasks the team should complete first. What project management value does this represent? A: Prioritization 2. When budgeting a project, what is the responsibility of a project manager? A: Controlling costs to ensure more money isn’t spent than what key stakeholders approved 3. As a project manager, you establish “escalation paths.” These allow you to quickly communicate task hindrances, also called roadblocks, to the right people. When escalating a roadblock, you document it and make sure everyone that needs to know is aware of the challenge. What project management responsibility does this represent? A: Ensure that issues and risks are tracked and visible 4. How can a project manager better communicate and clarify goals for a cross-functional team? A: Define key items and encourage team members to ask questions 5. You’re a project manager on a team that is ...

Project Management Weekly Challenge 8_Updating

  Project Initiation: Starting a Successful Project (W4) 1.  Fill in the blank: If the project has a _____, then it may be worth it for the team to learn a more sophisticated project management tool. A: large scope 2. What details should be in your project charter? Select all that apply. A: - Scope - Project goals - Deliverables 3. Who does the project manager need to get approval from before indicating a Go for the project? Select all that apply. A: - Project sponsor - Key Stakeholders 4. Fill in the blank: Project managers need to ensure project information is _____ through formal documentation, such as email, a presentation, or a digital document. A: Easily accessible to everyone 5. Email and chat are examples of what type of project management tool? A: Collaboration. 6. A project manager needs a tool to assign tasks and help visualize the team’s task progress. Which tool type should they choose? A: Work management 7. Fill in the blank: As a project manager, you may use Mi...

Project Management Weekly Challenge 11_Updating

  Project Planning: Putting It All Together (W3) 1.  When creating a budget, a project manager must do which of the following? Select all that apply. A: - Review and reforecast throughout the project - Budget for surprise expenses - Understand stakeholder needs 2. As a project manager creating a budget, you’re thinking about all the parts of a project from beginning to end—making a list of every material, resource, and contract worker. What do you call this type of budgeting A: Bottom-up approach 3. Which scenario is an example of proactive budget management? A: While planning your project budget, you gather historical data and consult with industry experts. You consider fixed costs, add relevant line items, and set aside a 5% reserve for unexpected costs. 4. As a project manager, you’re seeking a procurement approach that outlines clear workstreams, hard deadlines, and financially protects your project against unforeseen circumstances. Which procurement approach should you ch...